Lithuania and Poland need to finish Rail Baltica link by 2028 – minister

Lithuania and Poland need to finish Rail Baltica link by 2028 – minister

The projects for the onshore cable, Harmony Link, between Lithuania and Poland and the European standard-gauge railway Rail Baltica will be interlinked, particularly on the Polish side, so it is important for Vilnius and Warsaw to ensure that their railway lines are connected by 2028, a Lithuanian ministers said on Friday. 

“Undoubtedly, these projects are interdependent, especially on the Polish side,” Energy Minister Dainius Kreivys told reporters after a meeting of the Lithuanian government’s commission for the coordination of the Baltic power grids’ synchronisation with continental Europe.

Transport Minister Marius Skuodis said that 2028 is a key date for connecting the Lithuanian and Polish sections of the European-gauge railway.

“An additional energy dimension emerges now. We are also focusing on 2028, which is what we discussed in the commission, so here it is just important to make sure that we are connected in that year [2028], and not later,” he told reporters after the meeting.

The project for the railway track from Kaunas to the Polish border could be divided into separate stages to ensure that the Harmony Link and Rail Baltica projects do “not interfere with each other”, according to the minister.

Skuodis said that the planned power link will run alongside the railway for only four meters on the Lithuanian side, but for a much larger distance on the Polish side.

“I can see that solutions are already being found at a preliminary expert level, which is important from the Polish side. Because in Poland, the distances planned along the Rail Baltica route in kilometres would be quite different, so it is important to have these solutions on the Polish side,” Skuodis told reporters after the meeting.

“On the other hand, I can see an additional argument for our neighbours to move faster with the project, because it would not only be a strategic Rail Baltica project, but also an additional energy link,” he added.

The preliminary plan for the onshore Harmony Link, considered as an alternative to the initially planned submarine cable, sees a small section of the cable route – some 4 km out of about 30 km – in Lithuania run underground alongside the Rail Baltica embankment from the border with Poland to Kaunas.

While most of the link in Lithuania would be an overhead line, in Poland, plans call for laying an underground cable that would also require the Rail Baltica embankment.

Disclaimer

The Think Europe Services website is owned and operated by Think Europe Services Sp. z. o. o., a private international company operating independently from the Polish government. Please note that the information on this website is not intended as professional or legal advice. We make every effort to maintain the accuracy of the content, but it's important to be aware that certain terms, like immigration eligibility criteria, may be subject to change without prior notification. ..see more

In reference to our Job Search Service, we specialize in Resume Crafting, LinkedIn Enhancement, and Resume Promotion. It's crucial to emphasize that we do not promote job opportunities on behalf of international employers or serve as agents for any foreign companies. Our Registration number is KRS 0001007806, our tax identification number is NIP 9512557041, and all our services are exclusively offered at our Registered Center.

Please bear in mind that the content provided here is meant solely for informational purposes and should not be regarded as legal or tax guidance. It is recommended that you seek advice from your own legal and/or tax consultant(s). We do not offer legal or tax advice, and the information we present is of a general nature, not customized for any particular company or workforce. Moreover, it does not represent how we operate in a specific jurisdiction. We do not assume responsibility for the accuracy or timeliness of this information, and we are not liable for any losses that may occur as a result of using or relying on it.