Uncertain Waters: The Future of Poland's Deepwater Container Port Project

Uncertain Waters: The Future of Poland's Deepwater Container Port Project

Poland plans to develop a deepwater container terminal within a protected nature reserve in Świnoujście on the Baltic coast. Proponents highlight potential economic benefits, while critics, both locally and in Germany, worry about environmental impacts and whether local infrastructure can handle the increased cargo.

On the right bank of the Świna river, houses are stained grey by dust and coal emissions from the nearby port and liquefied natural gas (LNG) facility. Train tracks cut through deforested patches, and wild boar scavenge amid roadside litter.

In stark contrast, the left bank flourishes with lively seaside hotel resorts, attracting over two million tourists annually for its crisp air, expansive beaches, and unique biodiversity.

This division of Świnoujście, a port and resort town near the German border, may deepen as Poland’s new ruling coalition continues with the former government’s plans to construct a deepwater container terminal.

The terminal, adjacent to the LNG facility, will be situated within a nature reserve protected by the European Union’s Natura 2000 network.

Activists and some politicians in both Poland and Germany have opposed the project for years, predicting harmful environmental effects and a negative impact on local economies reliant on tourism.

Although the European Commission approved the plans in January, citing imperative reasons of overriding public interest, research by Notes from Poland suggests this decision should be viewed with skepticism.

**Underestimated Environmental Impact**

The deepwater terminal is to be built in an area home to common eiders and gulls, flounder and herring, and the occasional seal or porpoise.

Approximately 45 hectares of forest and dunes will need to be cleared for port, rail, and road infrastructure. Offshore, a container sea bridge, protective breakwater, harbor entrance, and turning basin will span around 350 hectares.

To allow 400-meter-long ships access to the port, 13 million cubic meters of seabed will be dredged and disposed of roughly 20 kilometers from the terminal. This will result in increased noise, traffic, emissions, and pollution, threatening several unique ecosystems protected under Natura 2000.

EU law and bilateral agreements with Germany required Polish authorities to conduct an Environmental Impact Assessment (EIA), allowing construction of the port only if the environment remained largely unchanged or if there were compelling public interests.

After presenting port plans in 2015, the former Law and Justice (PiS) government took five years to begin the EIA process, following inquiries from Polish MPs.

MEP Hannah Neumann, from Germany’s The Greens, notes that Polish authorities did not uphold the aforementioned agreements. They provided necessary German translations of documents only when asked and declared the EIA complete before the appeal period had ended.

According to the EIA published in October 2023 by the Regional Directorate for Environmental Protection (RDOŚ) in Szczecin, Poland will take compensatory measures to adequately protect the affected ecosystems.

These measures include using quiet technologies and relocating the affected Natura 2000 areas. The EIA also anticipates no significant impacts on Natura 2000 areas in Germany.

Activists and politicians from both Poland and Germany challenge these claims.

“It’s unlikely that such a large-scale intervention wouldn’t impact nearby areas. Nature knows no boundaries and operates as an interconnected system,” says MEP Helmut Scholz from Germany’s The Left.

Scholz, in collaboration with his European Parliament colleague Neumann, commissioned an independent assessment of the port project, which found that the expansion “would significantly affect flora and fauna on both sides of the German-Polish border.”

Meanwhile, Rainer Sauerwein, an activist and retired physicist, has filed a formal appeal with the Polish General Directorate for Environmental Protection (GDOŚ).

Sauerwein emphasizes that Poland’s current EIA only addresses the terminal’s immediate site, ignoring the impact of increased land and maritime traffic. “This oversight neglects amplification effects,” he says. “The EIA fails to assess the full impact scenario from Świnoujście to [German island] Rügen.”

The Polish authorities also announced a new sea access route in early 2023, for which they commissioned a feasibility study on 8 May. It is intended to replace the existing route, which runs partly through German waters and is too shallow for the ships the port in Świnoujście is intended to serve.

Sauerwein suspects political motives behind this decision: “By changing the route, they prevent Germany from saying no.”

Meanwhile, the Seaports Authority of Szczecin and Świnoujście (ZMPSiŚ) – the body responsible for managing the development of the port – has allocated 500 hectares of land for the project, without detailing their plans.

This decision was introduced through a special bill in the Polish parliament, without consulting the citizens of Świnoujście or the local government, and despite the environmental implications.

In their response to our inquiry, the ZMPSiŚ gave assurances that the land area of the terminal will not exceed 45 hectares.

“It is mainly an area for the construction of access infrastructure (road and rail) to the terminal and is not equivalent to the felling area. Tree cutting will be carried out only to the extent necessary,” the company wrote.

“If they only need 45 hectares, why take almost 500,” wonders Piotr Piwowarczyk, president of the Świnoujście Tourist Board.

**Disputed Economic Benefits**

Last year, the then deputy infrastructure minister Marek Gróbarczyk suggested that the deepwater terminal in Świnoujście would be “a second Hamburg,” referring to Germany’s busiest (and Europe’s third-busiest) seaport.

Numbers available on the project’s website and shared by politicians point to a target handling capacity of two million TEU (twenty-foot equivalent unit – the size of a standard shipping container) per year. Hamburg handled 7.7 million TEU last year.

Yet no studies have been conducted to analyze demand for the port’s services, says Rafał Zahorski, an expert in the maritime economy who advises both the local and national governments.

When asked about this, the ZMPSiŚ claimed that they “have for many years conducted their own analyses of the potential of the Baltic container shipping market in terms of locating a deepwater container terminal in Świnoujście.”

However, the ZMPSiŚ did not provide us with any materials to evidence this claim.

Likewise, the Polish infrastructure ministry – which also declares to have conducted market assessments – refused to share any documents, citing confidentiality.

Meanwhile, Maciej Brzozowski, a container shipping industry expert and head of the Port of Hamburg’s office in Poland, suggested to business website Money.pl that “so far none of the large shipowners or global terminal operators have been interested in this project.”

Zahorski estimates that the potential capacity should be closer to 400,000 TEU. “But if we take over 200,000 [TEU] it will already be a big success.”

For unloaded containers to be transported across Europe, a network of efficient railways and roads is necessary. Marek Grzybowski, president of both the Baltic Sea and Space Cluster and the Polish Nautical Society, supports the construction of the terminal but highlights that the current state of infrastructure might hinder its competitiveness.

The E-59 line between Malmö and Vienna connects Scandinavia with Central and Eastern Europe. Its CE-59 branch between Szczecin, Poznań, and Wrocław is reserved for freight traffic, however, the average speed of cargo trains traveling south on the line from Świnoujście does not currently exceed 20-23 km/h.

By comparison, the speed of trains carrying cargo from German seaports oscillates between 60 and 80 km/h.

“In Poland, one train can load about 80 TEU. Divide even just one million TEU by that, and then by 365 days a year. That’s about 34 trains a day,” Zahorski calculates.

Meanwhile, the S3 highway remains under construction. The government considers it “a key transportation corridor that opens Polish ports to central and southern Europe.” But Joanna Agatowska – a former member of the Świnoujście city council and the mayor of the city since April – voices her skepticism. “One lane of the S3 highway will be constantly occupied [by freight carriers], so we are left with only one lane for private vehicles,” she says, explaining that tourism in Świnoujście is already decreasing due to road traffic.

According to Agatowska, no buffer parking space has been added along the S3, increasing the likelihood of traffic and road congestion, and not enough space was left to expand the parallel railway.

Zahorski points out that even Germany – a country more experienced in containerization than Poland – struggled with its own deepwater terminal project. The JadeWeser port opened in 2012 in Wilhelmshaven was designed for 2.8 million TEU but currently handles only around 500,000 TEU.

**Management Controversies**

Further doubts about the project arise owing to the reputation of its management body, the ZMPSiŚ.

Agatowska feels that the city and its residents have been cheated by both the ZMPSiŚ and the former mayor, Janusz Żmurkiewicz, whose tenure overlapped with the 20 years he spent on the company’s supervisory board until 2020/2021.

As a councilwoman, Agatowska learned about the ZMPSiŚ’s plans to build a deepwater terminal after hearing a rumor from a colleague. She asked Żmurkiewicz about it at a city council session in late 2015, but he denied knowledge of the plans.

However, Żmurkiewicz and the ZMPSiŚ had already made an exploratory visit to the port of Algeciras in southern Spain “with the aim of learning about…an operating model that the Baltic port wants

 to transfer to its facilities,” reported local broadcaster Radio Bahia Gibraltar at the time.

After being called out by Agatowska, the mayor started to share more information. It emerged that around April 2016, the ZMPSiŚ had hired the consulting company Ernst & Young to conduct an initial economic analysis of the project.

Żmurkiewicz promised to conduct a local referendum about the terminal, but it was not held. Agatowska kept pushing for it and was eventually dismissed from her position as chairwoman of the city council.

The ZMPSiŚ continued its activities despite the aforementioned discrepancies. Politicians from the former PiS government made assurances about the necessity of the idea and its bright future.

But the project did not immediately attract investors. The April 2021 tender for its completion saw only one applicant – the UK-based Baltic Gateway Limited, which later turned out to have connections with the ZMPSiŚ board.

The company was not successful in its bid, yet may have created the illusion of interest in the project.

When a subsequent tender was opened, two companies – QTerminals from Qatar and the Belgian-based DEME – were selected to build the terminal and provide measures worth at least €5 million that benefit the local community.

But this amount will not even be enough to cover the road renovation, the cost of which is estimated at €5.5 million, explains Agatowska.

“Both companies are able to withdraw [from the agreement] at the snap of a finger,” adds Zahorski.

Asked about the two firms, Żmurkiewicz expressed his trust in them but admitted they had not considered the matter of accommodation for future employees.

When asked about the accommodation, the ZMPSiŚ said that “it should be expected that the terminal’s job offer will be aimed primarily at residents of Świnoujście and surrounding towns who have their own accommodation,” in spite of the fact that the city is depopulating.

Neither QTerminals nor DEME responded to our inquiries.

The credibility of the ZMPSiŚ has recently been further undermined by the so-called “pizza gate,” in which an audit showed that pizzeria owner Dariusz Śpiewak – an acquaintance of former PiS minister Joachim Brudzinski – was earning millions of zloty as a company executive employed on favorable terms.

“You know me, I rarely use strong words, but what we are finding at the Seaports Authority of Szczecin and Świnoujście is an absolute scandal,” Arkadiusz Marchewka, a deputy infrastructure minister in the government that replaced PiS in December, wrote in February.

Despite their initially critical stance towards the terminal and the aforementioned reputation of the ZMPSiŚ, the new Polish government has decided to go ahead with the project.

Due to the lack of consultation with local residents, Agatowska filed an appeal on 24 May against the West Pomeranian governor’s decision to locate the terminal in Świnoujście, expressing that “such a project has a chance only if it has social acceptance.”

Disclaimer

The Think Europe Services website is owned and operated by Think Europe Services Sp. z. o. o., a private international company operating independently from the Polish government. Please note that the information on this website is not intended as professional or legal advice. We make every effort to maintain the accuracy of the content, but it's important to be aware that certain terms, like immigration eligibility criteria, may be subject to change without prior notification. ..see more

In reference to our Job Search Service, we specialize in Resume Crafting, LinkedIn Enhancement, and Resume Promotion. It's crucial to emphasize that we do not promote job opportunities on behalf of international employers or serve as agents for any foreign companies. Our Registration number is KRS 0001007806, our tax identification number is NIP 9512557041, and all our services are exclusively offered at our Registered Center.

Please bear in mind that the content provided here is meant solely for informational purposes and should not be regarded as legal or tax guidance. It is recommended that you seek advice from your own legal and/or tax consultant(s). We do not offer legal or tax advice, and the information we present is of a general nature, not customized for any particular company or workforce. Moreover, it does not represent how we operate in a specific jurisdiction. We do not assume responsibility for the accuracy or timeliness of this information, and we are not liable for any losses that may occur as a result of using or relying on it.